← All projectsCC06248
Project portal · built 17 Nov 2026, 10:03 am AEST · Permits in force We supply traffic control

25-27 Boyd St, Tweed Head

Woollam

What's new

Monday updates and SharePoint changes, newest first

Full update log

Crompton Concepts prepares the traffic management for Woollam on this project at 25 Boyd St, Tweed Heads NSW 2485. No Monday request is open right now; the latest one closed recently; the current CTMP on SharePoint is Rev 04; 2 TGS suites on file (General Rev 01, S1 Rev 04). On the permit boards: 1 permit in force and 0 in progress. Monday holds 4 requests for this job (0 new, 4 amendments); all of them are on this page. Every file opens straight from SharePoint.

Client
Woollam
Crompton job
CC06248
Location
25 Boyd St, Tweed Heads NSW 2485
LGA / authority
Tweed
Project coordinator
D.B
Latest planner · TMD
—
Monday project status
New
Deliverables
TGS, TMP, Traffic Control, Police Permit, Council Road Permit, RA, Footpath Permit
Permits (Monday)
1 in force · 0 in progress
Last activity
20 Oct 2026
Files on SharePoint
166 in 43 folders

What needs attention now

  1. Nothing open on Monday. The latest request is closed or invoiced; this project stays on the list while it had activity in the last 120 days.

PPermits

1 permit line on the Monday permit boards: 1 in force, 0 in progress. Newest first within each state; closed and expired permits are at the bottom.

PermitAuthorityTypeStatusPeriodSentFollow upRenewalPermit no.
CC06248 - TWEED - Woollam - 25-27 Boyd St, Tweed Heads
Team Declan · Various Regional Councils - Declan
Regional councilOngoingIn force
Done
1 Jun 2026 – 1 Jun 20284 Jun 20261 May 2027

01New to the project? Start here

  1. 1

    Understand the job

    Start with the current traffic management plan, then the client's project information.

  2. 2

    Open the current TGS set

    Latest revision of each suite. Earlier revisions are in the register and the file list.

  3. 3

    Know the paperwork

    Project information, contacts, permits, quotes and invoices, as filed on SharePoint.

  4. 4

    Catch up on correspondence

    The latest emails saved into the project folder.

02Document register

Latest revision of each TMP, TGS suite and report, read from the revision folders and file names on SharePoint. Archived and superseded folders are left out.

SuiteDocumentLatestSavedRevsCurrent files
—CTMPRev 0418 Sep 20265CC06248-CTMP-Rev04-25-27 Boyd Street, Tweed Heads.pdf
—TMPRev 0418 Sep 20265CC06248-TMP-Rev04-25-27 Boyd Street, Tweed Heads.pdf
—RARev 011 Sep 20262CC06248-RA-S1-Rev01.pdf
—TIARev 021 Sep 20262CC06248-TIA Report.pdf
—Letter to residentsRev 021 Sep 20262CC06248-Letter To Residents.pdf
GeneralTGSRev 018 May 20251CC05635-Rev01- 25 Boyd St, Tweed Heads - CONCEPT.pdf
S1TGSRev 0418 Sep 20265CC06248-S1-TGS-Rev04- 25-27 Boyd Street, Tweed Heads.pdf

03Requests on Monday

4 requests since 7 Aug 2026: 0 for new plans and 4 amendments to this job, newest first. Amendments stay on this page, never as a separate project.

RequestTypeSuiteRevStageRequestedRequired byPlannerTMD
CC06248-S1 - Rev 4 - Woollam - 25-27 Boyd Street Tweed HeadsAmendmentS1Rev 04Closed
No Charge
18 Sep 202620 Sep 2026
CC06248-S1 - Rev 3 - Woollam - 25-27 Boyd Street Tweed HeadsCouncil RFIS1Rev 03Closed
No Charge
16 Sep 202618 Sep 2026
CC06248-S1 - Rev 2 - Woollam - 25-27 Boyd Street Tweed HeadsAmendmentS1Rev 02Closed
No Charge
31 Aug 20262 Sep 2026
CC06248-S1 - Rev 1 - Woollam - 25-27 Boyd Street Tweed HeadsAmendmentS1Rev 01Closed
No Charge
7 Aug 202611 Aug 2026

04Who's who

From the Contact folders on SharePoint and the people assigned on Monday. Check the project information folder for the latest contact list.

Crompton Concepts

  • DeclanProject coordinator (folder flag)
  • D.BProject coordinator (Monday)

05Update log

Monday updates and replies on this project's requests, newest first.

  1. 21 Sep 2026, 1:35 pm · Ripesh Mulmi · CC06248-S1 - Rev 4 - Woollam - 25-27 Boyd Street Tweed Heads

    @Accounts_Admin @Permits @Lexi R Accounts: 12x TGS Amendments (minor) 1x TMP Amendment Thank you.

  2. Hi, Please see instructions below: Plans Folder: 1. CC06248 Suite: S1 Please save work here; TGS > Rev 04 TMP > Rev 04 Project Location: 25-27 Boyd St, Tweed Head Request type: Amendment Scope: TGS & TMP Instructions from @D.B: "Hi Rihana, Can you please upload this as another revision please. TMP amendment as well. Planner is to change the pedestrian signage only to multi message QLD standards." Fw_ Pedestrian Detour - Boyd Street.eml thanks thanks ~ clint

    • 18 Sep 2026, 7:08 pm · Ripesh Mulmi

      @Christopher Wright Hi Chris!. Below Attached Amendment (TGS & TMP) for Review of CC06248-S1 - Rev 4 - Woollam - 25-27 Boyd Street Tweed Heads. TGS Link: Link: https://cromptonconcepts.sharepoint.com/Shared%20Documents/Forms/AllItems.aspx?id=%2FShared%20Docume... TMP/CTMP Link: Link: https://cromptonconcepts.sharepoint.com/Shared%20Documents/Forms/AllItems.aspx?id=%2FShared%20Docume... Accounts: 12x TGS Amendment 1x TMP Amendment Thank you.

    • 21 Sep 2026, 1:32 pm · Christopher Wright

      This is GTG @D.B

  3. Hi Team! NSW PLANS Plans folder: 1. CC06248 Suite: S1 Save work here: TGS > Rev 03 TMP > Rev 03 Project Location: 25-27 Boyd St, Tweed Head Request type: Amendment Scope: TGS & TMP Specific operations: CC06248-S1-3B - add a 1x TC for hold and release on Brett St traffic going east, and add a note advising TC will also help elderly and disabled people through the work area if needed CC06248-S1-4B - change the pedestrian detour into the parking lane rather then the detour around the block, and cover the pedestrain detour signs. Do the same for: CC06248-S1-9B & CC06248-S1-10B Thanks - Shaz

    • 16 Sep 2026, 9:52 pm · R.R

      Hi @D.B @Christopher Wright , TGS 3,4,9 & 10 amended. Files uploaded for review. Thank you. TGS: Sharepoint - Documents - Rev 03 - All Documents TMP: Sharepoint - Documents - Rev 03 - All Documents Accounts: 4x TGS amendments TMP amendment

    • 17 Sep 2026, 1:03 pm · Christopher Wright

      This is GTG @D.B

    • 17 Sep 2026, 2:43 pm · D.B

      Hi @R.R incorrect a little bit, the pedestrian detour was supposed to stay in place during the day. 3B, 9B With 1x TC for hold and release on Brett St traffic going east, and add a note advising TC will also help elderly and disabled people through the work area if needed. (but do not show the pedestrain detour through the site) (Keep pedestrian detour around the block) 10B & 4B are correct though Basically during the day, they send all the fit people around the block and show that detour on the TGS, with a note advising TC will help elderly and disabled people through the worksite. As during the day the site needs the footpath for the work area, and the parking lane for the workzone. and then at night they still occupy the footpath and send all pedestrians in the workzone/parking lane.

    • 17 Sep 2026, 3:01 pm · R.R

      @D.B Thanks for clearing this up. I’ll make the necessary modifications.

    • 17 Sep 2026, 6:20 pm · R.R

      @D.B updated now. Thank you

  4. No Charge

  5. Hi @D.B @Christopher Wright @A.A, For CC06248-S1 - Rev 2 - Woollam - 25-27 Boyd Street Tweed Heads, I've modified this following Teams discussion with Declan and Aaron. It is estimated that detour length is around ~650m. I've removed the lateral shift and have reflected this in both TGS and TMP. See change logs for each. Accounts: 4xTGS Amendment 1xTMP Amendment 1xRA Amendment Link: TGS > Rev 02 TMP > Rev 02 It is now available for review. Thank you!

  6. Hi @KB.R, For CC06248-S1-3B, CC06248-S1-4B, CC06248-S1-9B, and CC06248-S1-10B change the pedestrian detour to below, and remove lateral shift, just have the work area on the footpath and parking lane.

    • 31 Aug 2026, 2:22 pm · KB.R

      Hi @D.B @Christopher Wright @A.A, I’ve reviewed the proposed detour route and noticed that it does not appear to account for the pedestrian crossing near the worksite, specifically the crossing point near the roundabout. I’ve created a mock-up of the configuration shown in your markup and measured the detour to be approximately 523 m in length. However, I’ve also encircled the area where pedestrians are currently accessing the area, which does not appear to have been accounted for in the proposed arrangement. If these pedestrian movements are to be maintained and considered as part of the detour, the route would exceed the 500 m detour distance they are trying to comply with under Council’s guidelines. Would you be able to look into this and confirm how the pedestrian movements should be accommodated?

    • 31 Aug 2026, 2:32 pm · D.B

      @KB.R does NSW have footpath closed ahead signs? and the footpath closed signs go at the work area and the footpath closed ahead signs go where the current footpath closed signs are?

    • 31 Aug 2026, 2:40 pm · KB.R

      NSW do not have footpath closed ahead signs. Also, even if it was available, wouldn’t the measurement for the pedestrian detour commence from the point where the footpath is actually fully closed to pedestrian access, rather than from the location of the advance warning sign?

    • 31 Aug 2026, 2:45 pm · D.B

      @KB.R move the footpath closed sign on the right side, down to the work area please, but keep the other one where it is please, the detour will be more then 500m but that's fine.

06Every file and folder

166 files in 43 folders. Type part of a name, a suite, a revision or a street to narrow the list. Sort by name or by date saved.

TypeNameFolderSaved