← All projectsCC06536
Project portal · built 17 Nov 2026, 10:03 am AEST · TMD review

Oyster Creek Drive

Total Construction

What's new

Monday updates and SharePoint changes, newest first

Full update log

Crompton Concepts prepares the traffic management for Total Construction on this project at West Burleigh. 1 Monday request is open; the most pressing is at the TMD review stage; the current CTMP on SharePoint is Rev 04; 2 TGS suites on file (General no rev, S1 Rev 03). On the permit boards: 0 permits in force and 1 in progress. Monday holds 4 requests for this job (1 new, 3 amendments); all of them are on this page. Every file opens straight from SharePoint.

Client
Total Construction
Crompton job
CC06536
Location
West Burleigh
LGA / authority
—
Project coordinator
D.B
Latest planner · TMD
Kenny · Christopher Wright
Monday project status
New
Deliverables
—
Permits (Monday)
0 in force · 1 in progress
Last activity
17 Nov 2026
Files on SharePoint
82 in 29 folders

What needs attention now

  1. Needs TMD review: CC06536-S1 - Rev 2 - Total Construction - Storelocal West Burleigh. Required by 14 Nov 2026 (overdue). TMD: Christopher Wright · Last note (16 Nov 2026, S.B): “Hi Kenny, Thanks for the quick turnaround. The shuttle flow set (5A/B/C and 5D/E) reads well: stop/slow at both ends, PREPARE TO STOP and STOP HERE WHEN DIRECTED on each approach,…”
  2. Permit in progress: Daily Arrangement (Gold Coast) is Amendment Requested. Follow up 13 Nov 2026. Wanted from 19 Oct 2026.

PPermits

2 permit lines on the Monday permit boards: 0 in force, 1 in progress. Newest first within each state; closed and expired permits are at the bottom.

PermitAuthorityTypeStatusPeriodSentFollow upRenewalPermit no.
Daily Arrangement
Team Mackenzy · Gold Coast Permits - Mackenzy
Gold CoastOngoingIn progress
Amendment Requested
19 Oct 2026 – 19 Jan 202726 Oct 202613 Nov 20268 Dec 2026
LONO
Team Mackenzy · BCC CMP Lodgment / GCCC LONO lodgment
CMP / LONODate Specific
Done

01New to the project? Start here

  1. 1

    Understand the job

    Start with the current traffic management plan, then the client's project information.

  2. 2

    Open the current TGS set

    Latest revision of each suite. Earlier revisions are in the register and the file list.

  3. 3

    Know the paperwork

    Project information, contacts, permits, quotes and invoices, as filed on SharePoint.

  4. 4

    Catch up on correspondence

    The latest emails saved into the project folder.

02Document register

Latest revision of each TMP, TGS suite and report, read from the revision folders and file names on SharePoint. Archived and superseded folders are left out.

SuiteDocumentLatestSavedRevsCurrent files
—CTMPRev 046 Oct 20265CC06536-CTMP-Rev4- Oyster Creek Dr, Burleigh Heads.pdf
—TMPRev 046 Oct 20265CC06536-TMP-Rev4- Oyster Creek Dr, Burleigh Heads.pdf
—RARev 0025 Aug 20261CC06536-RA-S1-Rev0.pdf
GeneralTGSno rev28 Sep 20260TGS.pdf
S1TGSRev 0317 Nov 20264CC06536-TGS-S1-Rev3- Oyster Creek Dr, Burleigh Heads.pdf

03Requests on Monday

4 requests since 21 Aug 2026: 1 for new plans and 3 amendments to this job, newest first. Amendments stay on this page, never as a separate project.

RequestTypeSuiteRevStageRequestedRequired byPlannerTMD
CC06536-S1 - Rev 2 - Total Construction - Storelocal West BurleighAmendmentS1Rev 02TMD review
TMD Review
12 Nov 202614 Nov 2026KennyChristopher Wright
CC06536-S1 - Rev 4 - Total Construction - Storelocal West BurleighCouncil RFIS1Rev 04Closed
No Charge
6 Oct 20268 Oct 2026
CC06536-S1 - Rev 1 - Total Construction - Storelocal West BurleighAmendmentS1Rev 01Closed
No Charge
26 Aug 202628 Aug 2026
CC06536 - Total Construction - Storelocal West BurleighNew plansInvoiced
Invoiced
21 Aug 202628 Aug 2026

04Who's who

From the Contact folders on SharePoint and the people assigned on Monday. Check the project information folder for the latest contact list.

Crompton Concepts

  • KennyPlanner
  • Christopher WrightTMD
  • D.BProject coordinator (Monday)

05Update log

Monday updates and replies on this project's requests, newest first.

  1. Hi Kenny, Thanks for the quick turnaround. The shuttle flow set (5A/B/C and 5D/E) reads well: stop/slow at both ends, PREPARE TO STOP and STOP HERE WHEN DIRECTED on each approach, 40 km/h reduction, 60 m queue length, and footpath closure with DDA ramps. A few things to fix before it goes back to Macca: 1. Staffing (5A) * "Minimum TGS Assets" says TC (Including Breaks): 1, but the 5A manifest lists 2 x Traffic Controller and 5D has a STOP/SLOW TC at each end. A shuttle flow needs 2 TCs plus break cover. Please update the minimum assets line, and add a note that the two TCs keep radio contact (or have clear line of sight) to each other. 2. 0B Traffic Impact Analysis * Note 3 says "hold-and-release control during peak hours on Robertson St". That's copied from another job. It should be Oyster Creek Drive. * Note 1 wording is muddled ("2026 AADT Estimate gazettal is 1,993 VPD … and 1,984 VPD against gazettal"). Please state the volume for each direction clearly. * The 58 m / 34 m queues are based on a 2-minute hold for H&R. With the closed lane now extended, the shuttle hold time depends on how long it takes traffic to clear the single-lane section. Please confirm the 60 m design queue still holds for the extended length (or update it), and make sure the PREPARE TO STOP signs sit beyond the queue end on both approaches. 3. Speed on 5E * 5E shows a "60" and a "50" near the start of the sheet. If part of an approach is posted 50, the END ROADWORK speed plate on that side should…

    • 17 Nov 2026, 4:25 am · Kenny

      Hi @S.B Thanks for your comments. All the items raised have now been addressed in the updated TGS set. Please see the completed revisions below: Staffing (5A): Updated the Minimum TGS Assets to include two Traffic Controllers plus break cover. Added a note confirming that both TCs must maintain radio contact or clear line of sight with each other. 0B Traffic Impact Analysis: Corrected Note 3 to reference Oyster Creek Drive. Clarified the AADT volumes for each direction, reviewed the queue requirements for the extended closed-lane length, and confirmed the 60 m design queue and PREPARE TO STOP sign locations on both approaches. Speed on 5E: Reviewed and clarified the 50 km/h and 60 km/h speed signs, including the applicable END ROADWORK speed plates and title block information. Existing permanent signs have also been identified accordingly. Sign Manifest (5A): Completed a sign-by-sign…

    • 17 Nov 2026, 8:18 am · Mackenzy Moller

      @S.B Could i please have this reviewed this morning

  2. 16 Nov 2026, 11:48 am · Mackenzy Moller · CC06536-S1 - Rev 2 - Total Construction - Storelocal West Burleigh

    @Kenny Can you amend this urgently and then have TMD review i will need this by end of the day if possible @Riri D. @Christopher Wright

    • 16 Nov 2026, 11:50 am · Kenny

      On it @Mackenzy Moller

    • 16 Nov 2026, 12:42 pm · Kenny

      Hello Team, The TGS has been amended. Kindly review it at your convenience. 1x amendment CC06536-S1-5D/E (Closed lane extended) Folder Link: Rev 02 Thank you!

    • 17 Nov 2026, 6:56 am · Christopher Wright

      Hi @Kenny please ensure you allocate a colour in all closed section of the road, as this is a 60km/h road these distances are supposed to be 90m and 90m. the measurements you have used are for a 50km/h road. Please amend.

  3. Sent to client by Macca

  4. 12 Nov 2026, 11:29 am · Mackenzy Moller · CC06536-S1 - Rev 2 - Total Construction - Storelocal West Burleigh

    @Riri D. OH HOLD FOR NOW

    • 12 Nov 2026, 1:43 pm · Mackenzy Moller

      @Riri D. Please assign to a plan and have them to do a TGS for a shuttle flow

  5. Plans folder: Plans - CC06536 Suite: S1 Save work here: TGS > Rev 02 Project location: Oyster Creek Drive Quote: none Job request form: none Request type: Amendment Scope: TGS

    • 12 Nov 2026, 6:05 pm · Kenny

      Hi @Mackenzy Moller @Riri D. The TGS for shuttle flow has already been completed and uploaded to the folder. Please review it at your convenience. * ⁠1x Option analysis & Risk Assessment CC06536-TGS-S1-5A/B/C * 1x Additional TGS CC06536-TGS-S1-5D/E (Shuttle flow) Link folder: Rev 02Let me know if there is further need Thank you.

    • 13 Oct 2026, 9:04 am · Riri D.

  6. Hi Plans folder: Plans - CC06536 Suite: S1 Save work here: TMP > TMP > Rev 04 Project location: Oyster Creek Drive Quote: N/A Request type: Amendment Scope: TMP Specific operations: please see attached email for instructions Client mark-ups/attachments: Any specific files the planner needs to refer to? TRC_2026_2904 Oyster Creek Drive, BURLEIGH HEADS - DA-1061501.eml

    • 6 Oct 2026, 2:25 pm · R.R

      Hi @Christopher @Mackenzy , updated now. Thank you Link: Sharepoint - Rev 04 - All Documents Accounts: TMP amendments

    • 7 Oct 2026, 8:03 am · Christopher Wright

      This is GTG @Mackenzy Moller

  7. no charge

  8. Hi Planner, By following the below quote please create the below. TGS - Trucks nose in and nose out with hold and release of footpath Daily Operations (trucks drive in and out) starting 01/09/2026 - 01/09/2027 TGS - Trucks nose in nose out with footpath closed and pedestrians detoured into shoulder with hold & release of 1st live lane Date Specific, occupation of the footpath with pedestrains in shoulder starting at the start of next year TGS - After hours care - footpath open Daily aftercare plan for the duration of the project John Passaris | Contracts Administrator ‑ QLD Unit 13/16 Metroplex Avenue , Murarrie , QLD 4172 , Australia m. 0413 640 797 t. 07 3393 7700 Site Establishment Plan Rev3.pdf

    • 24 Aug 2026, 11:06 am · D.B

      @J.R please give me a call if you need help, reduce TC's more risk over more TC's, minimum TC's.

    • 24 Aug 2026, 11:12 am · J.R

      Hi @D.B, do you mean add 1 TC for relief/ TC breaks?

    • 24 Aug 2026, 11:14 am · D.B

      nah please don't show that TC for relief/breaks.

    • 24 Aug 2026, 11:15 am · J.R

      what does "reduce TC's more risk over more TC's, minimum TC's." mean?

    • 24 Aug 2026, 11:20 am · D.B

      Please keep the number of Traffic Controllers to a minimum. I’ve had several plans come back recently showing too many Traffic Controllers. Please review the setup and reduce the number of Traffic Controllers wherever possible.

    • 24 Aug 2026, 11:21 am · J.R

      @D.B make sense to me, thanks!

    • 25 Aug 2026, 12:01 pm · J.R

      Hi @Christopher Wright for review, thank you! Accounts: 3x TGS 1x Basic TMP 1x Short TIA 1x Desktop RA Please note the confirmation below for TGS 3: Thank you!

    • 26 Aug 2026, 9:43 am · Christopher Wright

      Hi @J.R Can you please make sure all TMP's have the TMR cert number changed to 0260. I have amended this one. @D.B This is GTG

  9. Hi, Save work here: 5. Plans - CC06536 Project Folder: Storelocal West Burleigh

    • 24 Aug 2026, 10:17 am · Riri D.

      Hi @J.R Declan will add more details of this job. Plans folder: 5. Plans - CC06536 Suite: S1 Save work here: TGS > Rev 00 TMP > Rev 00 Project location: Storelocal West Burleigh PLANS - Quote QU5456.pdf

    • 24 Aug 2026, 10:49 am · J.R

      Hi @D.B can you please provide the pin location for this allocation? Thank you!

06Every file and folder

82 files in 29 folders. Type part of a name, a suite, a revision or a street to narrow the list. Sort by name or by date saved.

TypeNameFolderSaved